Facility had been offline since 8 July.
RENOVA, Inc. said the Tokushima Tsuda Biomass Power Plant resumed normal operations on 25 July after completing repairs to a damaged steam control valve connected to the high-pressure turbine.
The plant, operated by RENOVA's consolidated subsidiary Tokushima Tsuda Biomass Power Plant G.K., had been offline since 8 July.
RENOVA said the outage falls within the range of unscheduled suspension days anticipated in the original operating plan for its biomass power generation business.
As a result, the company expects no impact on its consolidated financial results forecast for the fiscal year ending 31 March 2027. The company said it will disclose any further material developments if necessary.